Schedule & Budget

Preliminary Engineering Report - 
  • Completed March 2019
  • Budget - $467,500
Phase 1 Area - 30% Level of Design and Permitting
                       Started - December 2019
                       Public Meeting - Summer 2020
                       Anticipated Completion - December 2020
                       Design Budget - $1,690,000
                       
Phase 1 Area - Final Design and Permitting
                         Expected to start - early 2021
                         Budget - to be determined

Phase 1 Area - ROW, Easements and Constriction
                         Expected to start - 2022/2023
                         
Phase 2 Area - Design
                         Expected to start - 2023

For more information on this, or any City project, email Engineering Information.