Main Lift Station Force Main Replacement - January 2021
Diversion Channel: 100% complete
Storm Sewer: 80% complete along River Road with final completion scheduled after both proposed force mains are installed.
Force Mains: 85% complete; Force main line B will be installed up to the Wastewater Treatment Plant (WWPT) and then begin installing line A starting at the WWTP working back towards Cape Street.
Underground Bores: 12” reclaimed water bore is complete and the 24” force main bore under Cape Street is currently in progress nearing completion.
Reclaimed Water: Construction of bulk filling station to begin late January