Project Update - January 2021

  • Construction finished on manhole and bypass valve over existing force main, to bypass lift station
  • Slight delay on bypass pumping caused by different alignment of sewer services per design.  This has been resolved and additional work is underway so bypass pumping can continue. 
  • Work started to prepare lift station wet well for coating. Coating will be completed when bypass pumping in place
  • Work to start on concrete paving around lift station.