Project Name: Uhland Road Improvements

Current Update: 07/2021

Work Completed Last Month: Phase 1 (of 4) work includes –  Junction boxes completed for storm water. Stormwater quality device installed. Riprap installed for headwalls. Approximately 85% of waterline work complete in Phase 1. Gas relocation work started by CenterPoint. 

Work Planned This Month: Complete stormwater construction in phase 1. Start on road construction. Complete waterline work in phase 1.  

Construction Completion: See Dashboard For Details

Pictures from last month
Pavement removal in Uhland-River Intersection3Storm pipe stored on River rdView SE on Uhland towards low water crossing