Project Update

Project Name: Victory Gardens Subdivision Improvements

Current Update: 07/2021

Work Completed Last Month: Pavement along Patton Street from Armstrong Street to IH-35 Frontage Rd installed. Begin electric work along Patton Street from Roosevelt to Railroad.

Work Planned This Month: Complete electric work/services along Patton Street from Roosevelt to Railroad.

Construction Completion: See Dashboard For Details

Pictures from last month:


060321 Patton Conduits 500 blk (1)060321 Patton Conduits 500 blk (2)060321 Patton Conduits 500 blk (3)