Projects In Construction

Blanco Gardens

Blanco Gardens Drainage Improvements - CDBG-DR

Water Construction0%
Wastewater Construction0%
Stormwater Construction0%
Roadway Construction0%
% Contract Billed0%
Construction CompletionJune 2024
Project UpdateApril 2022


Feltner Alley Location Map - Copy

Feltner Alley Wastewater Replacement - 167

Water ConstructionN/A
Wastewater Construction60%
Stormwater ConstructionN/A
Roadway ConstructionN/A
% Contract Billed40%
Construction CompletionMarch 2022
Project UpdateApril 2022


Guadalupe St Improvements croppedGuadalupe St Improvements - Bike Lane Signal - 477

Water ConstructionN/A
Wastewater ConstructionN/A
Stormwater ConstructionN/A
Roadway Construction95%
% Contract Billed90%
Construction CompletionWinter 2022
Project UpdateMarch 2022




IMG_2558Guadalupe St Imp - Sidewalk and Landscaping - 477

Water ConstructionN/A
Wastewater ConstructionN/A
Stormwater ConstructionN/A
Roadway Construction75%
% Contract Billed70%
Construction CompletionWinter 2022
Project UpdateMarch 2022

Phase 1 - Mitchell intersection Concrete and Pavers Opens in new windowHopkins Street Improvements - Bishop to Moore - 90

Water Construction100%
Wastewater Construction80%
Stormwater Construction95%
Roadway Construction75%
% Contract Billed77%
Construction CompletionSummer 2022
Project UpdateMarch 2022


   Mobility IH 35 - IH35 and Hwy 123 Improvements - 629           

Mobility IH35 - Hwy 123 Detour

Water Construction50%
Wastewater Construction50%
Stormwater ConstructionCheck TxDOT Webpage
Roadway ConstructionCheck TxDOT Webpage
% Contract BilledN/A
Construction CompletionWinter 2025
Project UpdateMarch 2022

Mobility IH 35 - River Ridge Pkwy to Loop 82Mobility IH35 - River Ridge Pkwy to Loop 82 - 629

Water Construction90%
Wastewater ConstructionN/A
Stormwater ConstructionCheck TxDOT Webpage
Roadway ConstructionCheck TxDOT Webpage
% Contract BilledN/A
Construction CompletionSummer 2022
Project UpdateMarch 2022


CofferdamRio Vista Falls Maintenance - 743  

Water ConstructionN/A
Wastewater ConstructionN/A
Stormwater Construction50%
% Contract Billed28%
Construction CompletionSpring 2022
Project UpdateMarch 2022

                                                               

Sessom-TrafficControl2Sessom Creek Improvements Phase I - 521

Water Construction0%
Wastewater Construction75%
Stormwater Construction0%
Roadway ConstructionN/A
% Contract Billed14%
Construction CompletionFall 2023
Project UpdateMarch 2022


SWTP Improvements - Project Location Map

Surface Water Treatment Plant Improvements - 741

Water Construction
0%
Wastewater ConstructionN/A
Stormwater ConstructionN/A
Roadway ConstructionN/A
% Contract Billed0%
Construction CompletionSeptember 2023
Project UpdateMay 2022

  7-09-21 - 54in RCP into Stormgate collar 1Uhland Road Improvements - CDBG-DR

Water Construction40%
Wastewater Construction0%
Stormwater Construction45%
Roadway Construction28%
% Contract Billed35%
Construction CompletionWinter 2023
Project UpdateMarch 2022