Projects In Construction

Doghouse manhole after concrete pour Opens in new windowHills of Hays Lift Station Rehabilitation

  • Concrete almost finished around compound
  • Bypass pumping complete with wet well coated and new guide-rail system installed. 
  • Change order issued to extend duration due to delay with bypass pumping. 
  • Work to start on remaining items to complete project. This includes, fencing, gate, cleanup of electrical components, coating of valve chamber. 

Contract expended = 28%

Construction completion Spring 2021


Hopkins Before Photo ADA Ramp Opens in new windowE Hopkins - Bike and Pedestrian Improvements

  • Sidewalk & drainage nearly completed on the north side of Hopkins between Charles Austin and Thorpe.
  • Installing foundations for pedestrian lighting between Charles Austin and the Activity Center
  • Sidewalk & pavement widening at Charles Austin will occur next                               
  • % Contract Expended: 11.5%

Construction Completion: Summer 2021

hydrant at Travis Opens in new windowHopkins Street Improvements - Bishop to Moore

  • Construction continues on Phase 1 (Johnson Ave. to Endicott St) through March. Utility installation is also underway in Phase 2 (Bishop to Johnson Ave.).
      • Phase 1 utilities are 100% complete.
      • Phase 1 concrete is 90% complete.
      • Phase 1 lighting is 50% complete.
      • Phase 1 asphalt is 50% complete.
      • Phase 2 utilities are 30% complete.
  • % Contract Expended: 32.8%

Construction Completion: Spring 2022


Hunter Restriping - Bike Lane Thermoplastic

Hunter Road Re-striping Project

The roadway restriping was completed in December 2020, however the project was temporarily halted due to delays in shipment of the bike lane delineators.

Striping removal is 100% complete

Restriping is 100% complete

Installation of signage is 0% complete

Installation of bike lane delineators is 0% complete

% Contract Expended: 10.1%

Construction Completion: End of February 2021

Fusible PVC pipe for force main Opens in new windowMain Lift Station Force Main Replacement

  • Construction continues along River Road
  • Diversion channel is complete
  • Reclaimed water line bore under Cape Rd 100% complete
  • Two 24” force mains 90% complete (slight delays due to pipe realignment caused by unforeseen conflicts/conditions of existing utilities)   

5'x5' storm culvert along River Rd is 80% complete

Remaining 5'x5' culvert and 6 storm sewer crossings will be installed after completion of force mains

% Contract expended = 54.9%                                                                                                                                

Construction completion April 2021

Victory Gardens Subdivision Improvements1 Opens in new window

Working on Patton, Hines, Knox, Stillwell, & Wavell

Wastewater 95% complete (one repair on Camacho to be completed)

Water 95% complete

Storm sewer 90% complete

Rain gardens 70% complete

Road work 90% complete

% Contract expended = 83.7%


Construction completion March 2021

 


Wonder World/Hunter Preferred Alternative Opens in new window

Wonder World at Hunter Road Intersection Improvements

  • Construction concluded on Phase 4 (Southeast corner) on Monday, February 1st.
      • Phases 1-4 reconstruction is 100%  complete
      • Mill and Overlay is 0% complete
      • Restriping is 0% complete

% Contract Expended: 35%


Construction completion March 2021